Announcement
Collapse
No announcement yet.
Upping service and adding subpanel
Collapse
Forum Top GA Ad Widget
Collapse
X
-
I went over there yesterday and explained to them that to up the service they need bigger conduit, a new meter trough, going through the soffit attic and out through the roof because they are way below the current minimum height for lines, and a permit/inspection would be a must. They don't have a lot of extra money right now so we are just changing their 60A fuse panel to a 60A breaker panel and then doing a double pole 30A sub in the garage (he wants 220 out there).
Just curious, how many spots are in a typical 60A breaker box?
I noticed something else yesterday too. They ran out of spots in the fuse box so when the central furnace was put in they installed a switched fused plate mouted to a normal switch J-box and the wire is tapped right into the mains. I don't think that passes anymore, does it?
Thanks
Comment
-
[quote=DKAudio;26028]Ok Tom, I got another electrical job from a neighbor. Right now they have a 60A fuse box, the lines from the electric company look pretty small too. We are hoping they will handle 100A service. They are not pulling a permit or having it inspected even though I recommended it. Their electric meter is actually in the basement right next to the panel. Their weathercap and conduit are mounted under the soffit (does not go through the attic). It has a 90* bend and then runs down the exterior wall and into the basement.
This is what I am planning on doing.
Install new lines 4 AWG CU and weathercap to the line side of the meter and from the load side to the panel.
Replace their old 60A fuse box with a 100A breaker panel.
I will bond their water meter but probably won't drive a ground rod.
Install a 60A breaker sub panel in the garage. To do this I can just use a double pole 60A breaker using 6-3 with ground, correct? I know the sub panel must have an isolated neutral and ground will be bonded to the enclosure.
Code requires a ground rod at both locations. If the garage is attached.
Comment
-
Right now they have 8 spaces, 2 for 220V central AC pullout and 6 screw type fuses.
I know 100A is now the min but again, they do not want to replace the conduit, go through the roof to raise the height, do a new meter trough, etc.
They do indeed have 1" conduit, for 100A service I need a min of 1.25". As Tom pointed out earlier only 2 #4s can go in 1".
Thanks
Comment
Comment